Close Menu
  • Home
  • London
  • St Thomas
  • Toronto
  • Oakville
  • Ottawa
    • Hamilton
    • Richmond Hill
    • Vaughan
    • Windsor
    • Simcoe
    • St. Catharines
    • Thunder Bay
    • Tillsonburg
    • Vaughan
    • Wasaga Beach
    • Waterloo
    • Whitby
    • Windsor
    • Hamilton
    • Kitchener
    • Oakville
    • Ottawa
    • Perth
    • Peterborough
    • Pickering
    • Port Elgin
    • Renfrew
    • Richmond Hill
  • Contact us
What's Hot
Stefanie Fulawka Has Passed Away

Stefanie Fulawka Has Passed Away

May 9, 2026
Ontario Child Welfare Decision Faces Legal Challenge

Ontario Child Welfare Decision Faces Legal Challenge

May 9, 2026
Three Canadians Self-Isolating After Hantavirus Incident on Cruise

Three Canadians Self-Isolating After Hantavirus Incident on Cruise

May 9, 2026
Scarborough Southwest Liberals Choose Candidate Today

Scarborough Southwest Liberals Choose Candidate Today

May 9, 2026
Young Man Arrested for Alleged Hate Crimes Against Jews in Toronto

Young Man Arrested for Alleged Hate Crimes Against Jews in Toronto

May 9, 2026
Facebook Instagram
Facebook Instagram
Ontario ChronicleOntario Chronicle
Subscribe
  • Home
  • London
  • St Thomas
  • Toronto
  • Oakville
  • Ottawa
    • Hamilton
    • Richmond Hill
    • Vaughan
    • Windsor
    • Simcoe
    • St. Catharines
    • Thunder Bay
    • Tillsonburg
    • Vaughan
    • Wasaga Beach
    • Waterloo
    • Whitby
    • Windsor
    • Hamilton
    • Kitchener
    • Oakville
    • Ottawa
    • Perth
    • Peterborough
    • Pickering
    • Port Elgin
    • Renfrew
    • Richmond Hill
  • Contact us
Ontario ChronicleOntario Chronicle
Home»Kingston»Ajax Developer Ordered to Demolish Unauthorized Building
Views: 1709
Kingston

Ajax Developer Ordered to Demolish Unauthorized Building

March 29, 20264 Mins Read
Share Facebook Twitter Pinterest LinkedIn Tumblr Reddit Telegram Email
Ajax Developer Ordered to Demolish Unauthorized Building
Ontario developer loses appeal, ordered to tear down structure built without proper permits
Share
Facebook Twitter LinkedIn Pinterest Email
The Town of Ajax has secured a second legal victory against a Woodbridge developer, more than four years after the company started building a four-storey structure without the required permits.

On Thursday, the Ontario Divisional Court affirmed the demolition order for the property located at 599 Kingston Road West, rejecting an appeal from owner First Avenue following an unfavorable decision in September by the Superior Court of Justice.

The developer is now mandated to dismantle the partially completed structure at the southeast intersection of Kingston Road and Church Street in Pickering Village. Ajax Mayor Shaun Collier stated that the town, collaborating closely with legal counsel, will take “appropriate steps” to ensure that the demolition order is carried out.

Collier described this latest ruling as a “significant victory” for both the town and residents of Pickering Village.

“For years, our town has stood firm. Since 2021, we have worked through every necessary process with First Avenue, the Ministry of the Environment, Conservation and Parks and the courts to hold this project accountable,” Collier said in a statement. “This has not been a quick or easy fight, but we remained committed to defending our residents’ interests and upholding our planning and development regulations.”

“Today’s decision sends a clear message: our community will not be overlooked, and projects that ignore legal requirements will not be accepted in Ajax.”

Ajax Mayor Shaun Collier

First Avenue Properties acquired land on Church Street in Ajax back in 2015 with plans for a four-storey mixed-use development on what was previously an automotive repair shop that needed cleanup.

Diverse site plans were submitted to the Town of Ajax, leading to conditional approval granted to First Avenue in 2021. However, they did not secure a full building permit.

Court documents from Ontario’s Court of Justice reveal that by October 13 of that year, officials noticed construction activities were exceeding what was allowed under their conditional permit. This led to a visit from an inspector who spotted “above grade elements” being constructed.

“Not only did First Avenue lack a full building permit for these above-grade elements; they also neglected inspections for below-grade work. First Avenue admitted these points as true,” stated court reports.

The town promptly issued an Order to Comply requiring First Avenue to stop all work on above-grade components. However, upon inspection on October 27, it was found that construction continued despite this order.

Core slabs were later added on the second floor as structural support for walls without authorization from town officials, according to court testimonies.

The two parties have been locked in disputes ever since; meanwhile, construction remains unfinished at what should have been ground level since November 2021.

First Avenue argued before the court that demolishing their structure would be an unfair penalty due to factors beyond their control.

In her judgment last September, Justice Annette Casullo expressed strong disagreement with this view.

“First Avenue finds itself in these circumstances solely of its own accord. It failed to comply with terms it explicitly agreed upon,” she remarked. “First Avenue chose not to remediate the site-possibly due to high costs or perhaps because remediation wasn’t feasible. There’s no evidence explaining ‘why’ they opted against it; thus I needn’t reach any conclusion here.”

The developer suggested allowing them time instead of demolishing so they could work toward obtaining proper building permits.
However, Casullo ruled that First Avenue made a “calculated decision” when they built beyond what was permitted and “without following required inspections.”

“First Avenue’s actions should not be rewarded. A demolition order is justly warranted under these circumstances.”

This project is promoted online by First Avenue as ‘Five Nine Nine,’ which is presented as an upcoming low-rise modern apartment complex featuring carefully selected street-level retail spaces alongside parking facilities and waste management options comprising 60 one- and two-bedroom units.

No comments have been received from First Avenue Developments regarding this recent ruling despite requests for feedback.

INsauga’s Editorial Standards and Policies

Last 30 Days: 30,549 Votes

All Time: 1,273,186 Votes

1677 VOTES


Source link

appeal built developer Kingston Kingston news loses Ontario ordered Permits proper structure tear
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleMan from Toronto Arrested for Chop Shop Operation
Next Article Malnourished Boy’s Condition Discussed Before His Tragic Death
Casey Brooks
  • Website

Related Posts

Ontario Child Welfare Decision Faces Legal Challenge
Hamilton

Ontario Child Welfare Decision Faces Legal Challenge

May 9, 2026
Scarborough Southwest Liberals Choose Candidate Today
Oakville

Scarborough Southwest Liberals Choose Candidate Today

May 9, 2026
Trent University Tops Ontario’s Undergraduate Rankings
Peterborough

Trent University Tops Ontario’s Undergraduate Rankings

May 9, 2026

Subscribe to Updates

Stay updated with the latest news and exclusive content from Ontario Chronicle, delivered straight to your inbox. Sign up now and never miss a story!

loader

At Ontario Chronicle, we are dedicated to bringing you the latest news and updates from across the vibrant cities of Ontario, Canada. From the bustling streets of Brampton to the serene landscapes of Burlington, from the cultural hub of Hamilton to the historic charm of London.

We're social. Connect with us:

Facebook X (Twitter) Instagram Pinterest YouTube
Top Insights
Ontario Child Welfare Decision Faces Legal Challenge

Ontario Child Welfare Decision Faces Legal Challenge

May 9, 2026
Three Canadians Self-Isolating After Hantavirus Incident on Cruise

Three Canadians Self-Isolating After Hantavirus Incident on Cruise

May 9, 2026
Body Discovered in Vehicle Fire in Chippewas of the Thames

Body Discovered in Vehicle Fire in Chippewas of the Thames

May 9, 2026
Facebook X (Twitter) Instagram Pinterest
  • Home
  • About us
  • Contact us
  • DMCA
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions
© 2026 OntarioChronicle.

Type above and press Enter to search. Press Esc to cancel.

Subscribe to Updates

Stay updated with the latest news and exclusive content from Ontario Chronicle, delivered straight to your inbox. Sign up now and never miss a story!

loader

✅

You're Subscribed!

Thanks for subscribing to Ontario Chronicle. You'll start receiving updates shortly.