Major Loss on Southern Ontario Home Sale

Major Loss on Southern Ontario Home Sale

August 5, 2026
Uncertainty Grows as Ontario Teacher Negotiations Hit a Snag

Uncertainty Grows as Ontario Teacher Negotiations Hit a Snag

August 5, 2026
Missouri, Kansas voters reject giving GOP more power

Missouri, Kansas voters reject giving GOP more power

August 5, 2026
MBC Launches New Radio Formats in Tillsonburg

MBC Launches New Radio Formats in Tillsonburg

August 5, 2026
Hamilton Awards IMCO a 0 Million Pension Contract

Hamilton Awards IMCO a $300 Million Pension Contract

August 5, 2026
Facebook Instagram
Facebook Instagram
Ontario ChronicleOntario Chronicle
Subscribe
  • Home
  • London
  • St Thomas
  • Toronto
  • Oakville
  • Ottawa
    • Hamilton
    • Richmond Hill
    • Vaughan
    • Windsor
    • Simcoe
    • St. Catharines
    • Thunder Bay
    • Tillsonburg
    • Vaughan
    • Wasaga Beach
    • Waterloo
    • Whitby
    • Windsor
    • Hamilton
    • Kitchener
    • Oakville
    • Ottawa
    • Perth
    • Peterborough
    • Pickering
    • Port Elgin
    • Renfrew
    • Richmond Hill
  • Contact us
Ontario ChronicleOntario Chronicle
Home»Pickering»Darlington Nuclear Project Finishes Early and Under Budget
Views: 344
Pickering

Darlington Nuclear Project Finishes Early and Under Budget

August 5, 20263 Mins Read
Share Facebook Twitter Pinterest LinkedIn Tumblr Reddit Telegram Email
Darlington Nuclear Project Finishes Early and Under Budget
Share
Facebook Twitter LinkedIn Pinterest Email
The refurbishment of the fourth Candu reactor at the Darlington nuclear power station in Ontario, Canada, has wrapped up four months ahead of schedule and CAD150 million (€92 million, $109 million) under the total budget of CAD12.8 billion.

Unit 4 was the last reactor to be refurbished in this four-unit project that kicked off in October 2016 with Unit 2’s upgrades.

On February 2, the Ontario government announced that Unit 4, which is an 878-MW Candu unit that started commercial operations back in 1993, is expected to be back online later this month. The staff at the station are currently finishing up final tests before returning to full commercial operation.

The statement indicated that this significant project ensures over 3,500 MW of clean, dependable energy for Ontario’s expanding electrified future. It also highlighted that this refurbishment is the largest completed nuclear refurbishment globally and will generate enough electricity to power around 3.5 million homes while supporting approximately 14,200 jobs over the next three decades.

The Darlington refurbishment involved a complete revamp of all four nuclear reactor units, extending the lifespan of the station until at least 2055.

This work included replacing thousands of fuel channels, feeder tubes, calandria tubes, and end fittings along with restoring other essential components. The initiative also featured system enhancements and plant upgrades to comply with regulatory standards.

Nuclear Energy Remains Essential for Ontario’s Clean Grid

Nuclear energy continues to be a key part of Ontario’s clean electricity supply, accounting for about half of the province’s energy needs.

Ontario Power Generation (OPG), which owns and operates Darlington, mentioned it will apply insights gained from this project to ensure success in its small modular reactor (SMR) initiative at Darlington as well as during renovations at the Pickering nuclear station.

In May, both the Ontario government and OPG greenlit plans to construct one out of four BWRX-300 SMRs at Darlington.

In November, OPG received official approval from Ontario to start refurbishing four nuclear units at Pickering.

The overhaul plan for Pickering’s four units shares some aspects with Darlington’s lengthy life-extension work-like replacing 380 fuel channels per reactor-but involves greater complexity. Unlike in Darlington’s case, Pickering’s project will require replacing all 48 steam generators-a first for Ontario’s Candu reactors.

This initiative also includes building a new deep-water intake system stretching 1.5 kilometers to access cooler cooling water-a feature missing from Pickering’s original design.

Energy Minister Stephen Lecce stated: “In a world of uncertainty, our government is doubling down on Canadian nuclear technology and workers, with 96 percent of investment benefiting Ontario’s supply chain.”

“It is a tremendous industrial advantage that Canada is among only six nations that own civilian nuclear technology; yet we stand alone as number one in building, operating and refurbishing projects on-time and on-budget.”

OPG is set to begin refurbishing four nuclear power units at Pickering. Courtesy OPG.


Source link

ahead budget CAD150 completed construction Darlington million Nuclear Pickering Pickering news Refurbishment schedule
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleRising Heat May Increase Tornado Activity in Ontario
Next Article Peterborough’s Waste Facility Grapples with Tire Backlog
Taylor Spencer
  • Website

Related Posts

Hamilton Awards IMCO a 0 Million Pension Contract
Hamilton

Hamilton Awards IMCO a $300 Million Pension Contract

August 5, 2026
Ontario Hospitals Facing Over 0 Million in Deficits
Thunder Bay

Ontario Hospitals Facing Over $400 Million in Deficits

August 5, 2026
Major Manufacturing Boost in Burlington with 2 Million Investment
Burlington

Major Manufacturing Boost in Burlington with $132 Million Investment

August 5, 2026

Subscribe to Updates

Stay updated with the latest news and exclusive content from Ontario Chronicle, delivered straight to your inbox. Sign up now and never miss a story!

loader

At Ontario Chronicle, we are dedicated to bringing you the latest news and updates from across the vibrant cities of Ontario, Canada. From the bustling streets of Brampton to the serene landscapes of Burlington, from the cultural hub of Hamilton to the historic charm of London.

We're social. Connect with us:

Facebook X (Twitter) Instagram Pinterest YouTube
Top Insights
Hamilton Awards IMCO a 0 Million Pension Contract

Hamilton Awards IMCO a $300 Million Pension Contract

August 5, 2026
23-Year-Old Faces Charges After Shooting in London

23-Year-Old Faces Charges After Shooting in London

August 5, 2026
Hamilton Beer Store to Close by Mid-August

Hamilton Beer Store to Close by Mid-August

August 5, 2026
Facebook X (Twitter) Instagram Pinterest
  • Home
  • About us
  • Contact us
  • DMCA
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions
© 2026 OntarioChronicle.

Type above and press Enter to search. Press Esc to cancel.

Subscribe to Updates

Stay updated with the latest news and exclusive content from Ontario Chronicle, delivered straight to your inbox. Sign up now and never miss a story!

loader

✅

You're Subscribed!

Thanks for subscribing to Ontario Chronicle. You'll start receiving updates shortly.