The primary part of rehabilitation work on a serious Walkerton bridge is projected to wrap up in February.
Bruce County’s Transportation and Environmental Providers division says the rapid half-joint restore work being accomplished on the Durham Road Bridge is on funds and progressing nicely.
The bridge has been lowered to 1 lane of alternating site visitors all through a lot of the work, which started in Could. The development is projected to be accomplished in late February 2025.
The County says it expects each lanes to be open on the bridge as soon as Part 1 work is full. Weight restrictions will even be reassessed at that time.
Nonetheless, there may be nonetheless a second part of labor that must be accomplished as a way to prolong the lifetime of the bridge. The Schedule ‘C’ Environmental Evaluation for that venture was just lately accomplished, so workers anticipate that work to get underway shortly following Part 1.
Lane closures will tentatively be in place in Spring 2025, with the expectation that Part 2 can be accomplished by Fall 2025.